Schedule:

Project Schedule:  July 2020

Project Scope:  Strip and refinish brightwork; sand and prime hull (no paint)

Project Complete:  16 total hours

Begin Daily Project Logs

July 10, 2020

Maya 10

Friday

The primer was well-cured overnight, and to begin I lightly sanded the hull to smooth the primer and prepare it for whatever topcoat the owner chose (final painting was outside my project scope).  It was easy and quick to sand the primer, and afterwards I removed the masking tape, vacuumed, and solvent-washed to complete the project.

<Back to Maya

Total time billed on this job today:  .0.5 hours