Schedule:

Project Schedule: May – June 2020

Project Scope: Minor brightwork and exterior maintenance

Project Complete:  7.5 Total Hours

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

June 2, 2020

Rocket 4

Tuesday

I began the day with a light sanding of the coamings, and then the primed rubrails.  After the usual rounds of cleanup, I applied a full coat of maintenance varnish to all areas of the coaming.

Later in the day, I received the paint I’d ordered for the rubrail.  Anticipating the delivery, I was ready to go once it arrived, and in short order applied the first of at least a couple coats of the new paint.  I chose a a traditional, yet fun, color called “tint green” in a semi-gloss finish, which I thought would be a nice accent for this boat (and was).

Total time billed on this job today:  1 hour

0600 Weather Observation:  31°, clear with fog.   Forecast for the day:  Sunny, 66°