Snow Lily | Wednesday, June 5, 2013

Continuing the basic check-out of the new systems, I connected the shore power and checked the operation of the main breaker (operational) and shore power charger, the only device attached to the shore power.  I also checked the tablet-based display for the battery monitoring system for basic operation; a few screen shots are shown below.




         


I added some straps to secure the battery cover and by default the batteries beneath.

    

While a few small items remained outstanding, pending delivery of a couple severely backordered items and some canvaswork miscellany, plus final pre-launch tasks, at this stage the project was essentially complete, and it was time to make final arrangements.



         

         

    
 


Total Time on This Job Today:  1.75 hours