After a final round of cleanup, I installed epoxy fillets at the edges of the bulkheads in the main cabin, for which I'd previously prepared cut tabbing.  This included the main port bulkhead, its counterpart to starboard, and one side of the bulkhead defining the galley.


         


Once the fillets had cured sufficiently, which didn't take long in the warmth of the day, I installed two layers of biaxial tabbing, overlapping seams between the layers as needed.  With some time remaining in the day, I prepared additional fiberglass for other sections of these and other bulkheads that I'd install net.

       


Total Time on This Job Today:  6 hours