Kaholee Refit | Final Phase Work List (as of 11/11/07 2/22/08 5/02/08 5/5/08 5/20/08 5/21/08 6/5/08 6/27/08 6/28/08 7/8/08)

 
  • Install chafe gear around portions of exhaust hose (material on hand and installation expected soon)
  • Measure for new propeller shaft, Cutless bearing, and stuffing box, and order as necessary
  • Install traveler turning blocks in conjunction with dodger installation
  • Install cockpit table bracket
  • Install bronze mooring bitt and bow and stern chocks (parts on hand)
  • Install split loom over port speaker wire (material on hand)
  • Obtain and install transducer security pin that fits in the space provided
  • Fabricate and install bracket for LPG tank, solenoid, and regulator, and complete hose connections
  • Modify cook stove LPG connection to accept proper flare nut connection
  • Figure out means of locking cook stove in non-gimbal mode
  • Install roller furler; modify headsail as required
  • Determine status of standing and running rigging
  • Install mast wiring and new lighting as required
  • Fabricate and install a few minor interior trim pieces (engine box, v-berth)
  • Install catches on locker doors
  • New boom?
  • Strip and Repaint Mast
  • Install cabin blinds
  • Replace stern tube and install shaft, stuffing box, propeller, and Cutless bearing
  • Paint bottom
  • Replace fuel fill cap--spring stopped working
  • Make and install winch fairing blocks for mast halyard winches
  • Conceive and install mainsheet system
  • Halyard shackles
  • Install autopilot tiller pin and receptacle in cockpit seat
  • Install radar pole
  • Install solar panel mount and solar panel
  • Install genoa tracks (fully rigged boat required)
  • Install through-deck connection for mast wiring and connect wires as necessary
  • Install GPS and VHF antennae
  • Ongoing punch list of minor items nearly complete