|
|||
|
~ The bLog Home ~ |
||
THURSDAY, AUGUST 31, 2006 |
|||
I continued work on the plumbing this morning while I waited for Bob to arrive to help build the truss in the great room (built in place). I ran some additional supply lines until I ran out of clamps for securing the pipe. Then I busied myself with a few other things till Bob arrived at 8 or so. | |||
Our first order of business was to assemble pipe staging again so that we could reach the ridge--always a fun time. Then we turned our attention to the task at hand. The single truss in the great room serves only to support the longest ceiling tie--the one closest to the gable end--that helps prevent the house walls from spreading under the roof load. We were to build the truss in place; three of the truss members were already in place: the two roof rafters and the horizontal tie at the bottom. We needed to add four additional pieces to create a "W" shape in between the original three pieces. After consulting the drawing for the general design of the truss, we decided to loft the layout on the floor so that we could properly come up with the correct angle cuts at the ends of the truss members. We took a couple measurements up in the ceiling as necessary, and then transferred them to the floor. It's funny how small the layout looks when on the floor, as opposed to gazing up into the heights of the ceiling. |
|||
Once we had the layout, we cut the first piece. Getting it into place was fairly easy: we stood it up next to the staging, then I climbed partway up and held it while Bob went to the top. Then, we simply lifted the beam into its proper position. The first piece fit to within 3/8" of the mark on the horizontal tie piece, which was 1/3 of the total chord length (of the tie) to the wall. That was certainly within tolerances, and we used a couple log screws to secure the piece; the screws would be hidden by other parts of the truss later. |
|||
![]() |
|||
![]() |
|||
In fact, the truss looked a lot like the "big W" from this classic comedy. You get bonus points if you can name the movie. |
|||
|
|||
![]() |
|||
![]() |
|||
![]() |
|||
With what time remained in the day, I started to build the shower enclosure in the upstairs bathroom, now that the tub was inside and I didn't need the open space. I had previously laid out the floor with the shadow of the shower walls, so building a couple small walls was straightforward. I built the two side walls, but didn't get to the very short angled wall before the end of the day. I had accumulated a healthy list of plumbing supplies needed in order to continue my plumbing tomorrow and over the long weekend, and I certainly didn't plan on heading to Lowes or Home Despot on labor day weekend, so I planned to make the trek to Lowes first thing in the morning, as usual. I had some expensive items to return--those silly plastic manifolds, for example--so I decided to drive all the way to Lowes instead of to the closer Home Despot. |
|||
WEDNESDAY, AUGUST 30, 2006 |
|||
![]() |
|||
![]() Once the box was lifted, though, a problem became apparent: there was a steel projection at one end of the box (the open end) that wanted to hit the roof overhang before he could get the box high and close enough to the window opening. Plan B was to remove the plywood from the opposite end of the box, which didn't have the extra metal, which fortunately was pretty easy to do as well as ultimately effective. |
|||
![]() |
|||
![]() Afterwards, I got back to work and finished up the electrical panel. I ended up with one too many circuits, interestingly enough. It took me several minutes to figure out what had happened. I had originally wired for some lights to be mounted on the wall on either side of the bed in the bedroom, but we decided that table lamps would be the way to go instead. So I abandoned these wires, which had ended up alone on the circuit when I had to reconfigure the lighting circuit with Heidi's office lights (I described this process last week). "Circuit 15" therefore became available once again, and later on in the process I chose that designation for, as it turned out, two separate circuits, failing to properly mark this down on my sheet. Fortunately, GE makes 1/2" wide breakers as well as the standard 1". This means that I can buy two of the 1/2" size and install them in the space normally required by one breaker, which will allow me to wire both circuits properly. For now, I left one of the "15" circuits unattached. |
|||
![]() I headed to the basement to check, and that's when it clicked: during panel wiring, I had switched the circuit I had called #1 with #11, as the wire for #11 ended up too short to reach that far into the box. (This was one of the wires I had damaged with the drill the other day; repairing the wire with a junction box had shortened the wire some.) I switched on circuit 11 and all was well. |
|||
I spent the rest of the day on plumbing. I chose PEX tubing for my supply lines, mainly because the cost of copper had risen so high of late. PEX, the trade name for cross-liked polyethylene tubing, is the same material used in radiant heat floors, and is becoming increasingly common for plumbing systems, replacing copper and sweat joints. PEX has the added benefit of fewer connections that might leak, as I planned to run each fixture's supply back to a master manifold in one continuous run, versus copper where various lines are teed off each other and so forth.
Before long, I decided to build my own manifold using copper pipe. I had to use copper to run the main supplies to the PEX in the first place, and decided that it would make a much better installation if I built my own system of piping and valves. I removed the cheesy manifolds and replaced them in their boxes for return. |
|||
![]() PEX requires a few specific tools: a crimp tool (for the little black crimp rings), a test device (the little gauge shown here) to determine if the rings are crimped correctly, and a pair of cutters. |
|||
![]() |
|||
TUESDAY, AUGUST 29, 2006 |
|||
I began with an early morning trip to Home Despot to pick up some additional wiring supplies and to also pick up more PEX plumbing supplies. I had been having a tough time finding all the parts I needed for the PEX tubing and was anxious to get going on the water supply lines. I found enough stuff that I thought would do what I needed, but undoubtedly there will be things I don't have. | |||
Back home, I had only just arrived when the truck from Moose Creek arrived--perhaps the earliest delivery on record. I had ordered the interior V-match pine boards for the areas we intended to use pine, and also had ordered all my interior trim material (pine), as I could begin putting trim on the windows and doors in the log walls immediately. I had hoped that the boom truck would bring the load, and that maybe I could get the driver to help me load the bathtub upstairs. Alas, it was the small, boomless truck.
Once the delivery truck left, I headed for the yellow pages to seek out an alternative to get the tub into the house. Earlier reconnaissance had pointed me to a local construction company that advertised boom truck service, and I called and left a message. Late in the afternoon, I received a call back and set up an appointment to boom the tub in tomorrow morning first thing--excellent! |
|||
![]() |
|||
![]() |
|||
![]() |
|||
![]() In several hours during the afternoon, I completed one side of the panel. With the bulk of organization and preparing out of the way, I expected to be able to easily finish the panel wiring in a short time in the morning. Then, I planned to get going on the plumbing supply lines. I really wanted to meet my goal of having all the systems roughed in before September 1. |
|||
MONDAY, AUGUST 28, 2006 |
|||
![]() |
|||
![]() |
|||
It took some time to repair the damage caused by an idiotic tool operator; I had to replace one wire and still needed to install two junction boxes, since I wasn't about to pull all the wires out of the wall to replace the full lengths. I was furious with myself, of course. |
|||
![]() |
|||
SUNDAY, AUGUST 27, 2006 |
|||
It was another full day of wiring. I continued my work on the second floor and pulled any remaining wires through the walls as needed. I began by installing junction boxes and splicing the wires for Heidi's office lighting that I made a mistake in on Friday. | |||
Then, I concentrated on completing a couple of the more difficult runs, including getting the wires I ran yesterday from the back wall out to the edge of the loft, where they'd run onto the ceiling ties for lighting there, and around to the final ceiling tie in the great room, the one closest to the gable end, which required two wires: one for the dining room chandelier and one for the other lights. |
|||
Since this final tie was of course surrounded by log walls and finished, exposed ceilings, I probably should have run some wires somehow during initial construction of the roof. But I didn't, and now needed to figure out how to get them there. Fortunately, there was a handy open, unfinished soffit out back that might provide me the access and wire chase I needed. |
|||
![]() |
|||
![]() |
|||
![]() |
|||
![]() By early evening, I finished up all the wiring on the second floor during the remainder of the afternoon, including pulling all the coax cable, phone, and Internet cables to each of six locations, and then cleaned up the wood chips and so forth. It looked like I could probably finish up the wiring tomorrow. |
|||
SATURDAY, AUGUST 26, 2006 |
|||
I worked on the wiring from about 7 to noon, pulling many of the lighting circuits up to the second floor. This included many of the longest wires, which I had to run from the switch center (in the stud wall beneath the stairs) through the basement, over to the main wet wall (where I was running most of the wiring upstairs), and then across the studs at the back wall of the house to their ultimate destination. I also ran circuits to the bathroom and vanity lighting, as well as the closet light. | |||
![]() |
|||
![]() We had some house-related errands planned for the afternoon, centered around a trip to the tile store to work out what we needed for the two bathrooms. It was time to choose and order these finish materials, and as much as I hated to take any time away from working on the house, it had to be done. I couldn't find the hours for the tile store on their website early in the morning before I went to work, but figured they'd be open all day, as is the norm. |
|||
We departed here about12:45, and after a trip to the home center for more wiring supplies, headed to Portland to the tile store. As we approached, I didn't see any cars in the lot. Uh-oh. It turned out they closed at 2. (It was 3 PM now.) What an idiot! We salvaged the afternoon by going to the lighting store instead. |
|||
FRIDAY, AUGUST 25, 2006 |
|||
![]() |
|||
I began the day running 12/2 wiring to the receptacle boxes upstairs. I believe I ended up with 3, or perhaps 4, circuits. Three, I think, which was fewer than I had expected for some reason. In any event, I ran a couple of the circuits through the interior plumbing wet wall at the back of the house, and then ran the additional one through the interior stud walls next to the staircase. | |||
![]() Lighting circuits are complicated by the need for switches. In a log cabin, with the solid exterior walls and exposed beam ceilings, providing switches for all the lighting becomes even more challenging. During log construction, I had decided against installing most of the switches in any of the log walls, planning instead on a sort of "control center" on the interior stair wall. Despite the extra long runs required to bring most of the lighting circuits through this wall, I figured it would be more convenient than having to run so many wires into the log walls, particularly at switch height. |
|||
![]() |
|||
![]() |
|||
![]() By the time I noticed this blatant error, I had of course already secured all the wires that I had run with multiple wire clamps, and besides: I was certainly not about to pull those wires out of their hard-one chases. Still, I needed these wires to run through a switch box in Heidi's office. Therefore, I had no choice but to run a new wire to the craft room lights through a switch box in the craft room below, which meant I would need to create a splice in a junction box in the master bedroom above. I prefer to avoid splicing and junction boxes, but there was no other choice here. Of course, I had no junction boxes on hand, so I put them on the list for my next trip out into the world. No real harm done...but I kicked myself for this idiotic and avoidable error. Fortunately, I had plenty of extra wire already in the circuit right nearby, as I had planned a wall fixture above and had left a small coil of wire there, not knowing exactly where it would end up. I pulled this wire out of the wall and left it on the floor so that I'd remember to create the junction box later. I'd also need to run a short length of new wire to connect the other lighting fixtures. Running the new circuit and additional wire took up the last part of the afternoon. By now, after 11 hours, I had been up and down the two sets of stairs in the house dozens of times, and between that and the constant kneeling and up and down, I felt like I'd biked the Tour de France. I figured I'd recover by the morning, though. |
|||
THURSDAY, AUGUST 24, 2006 |
|||
![]() It took me much of the morning to finish laying out the remaining vents and drains for the upstairs bath fixtures. Working from the downstairs bathroom, I continued where I left off yesterday and managed to get everything fit together dry. Then, I had to mark everything and dismantle the pipes so that I could glue all the joints. |
|||
![]() |
|||
![]() Now all I need is my plumbing inspection, and the job will truly be done. I planned to call the inspector on Friday. I don't think he cares about potable water piping, but I'll find out. |
|||
![]() Finally, I measured for some of the V-match pine paneling that we planned to install in a few areas inside the house. Many of the interior walls, minimal as they are, will be drywall, or some combination of pine and drywall, but anticipating a materials order very soon--like tomorrow--I decided to figure out roughly what I might need. Once the potable water plumbing and rough electrical are complete, I can start covering the walls! I expected to have most of this done by the end of the weekend, or early next week. Things were looking encouraging for me to meet my goal of having all the systems work done by the end of the month. |
|||
WEDNESDAY, AUGUST 23, 2006 |
|||
I drove down to Lowes again with my truck full of plumbing fittings to return. I figured it was better to just get it done. I wasn't looking forward to the process, but couldn't wait to rid myself of the fittings and get a hefty refund to boot. I was at the door when the manager opened it at 6, and spent about 40 minutes at returns getting the stuff credited. Then I went and bought all kinds of stuff, including more wire--14/2, 14/3, 12/2, and 10/3. I was happy to see that the price had dropped significantly since my last purchase, though it was still pricey. I also bought some select plumbing fittings that I now knew I would need, and some fittings for the PEX potable water pipe. | |||
![]() With the unconventional construction of the house, venting each fixture is more of a challenge, but I thought I understood. The thing is, I knew the system would work fine. What I didn't know was what sorts of things our plumbing inspector might look for, or if he would be a stickler for some detail or another. Past experience would not seem to indicate that he'll be a pain, but nonetheless I worried a bit since I didn't really know what was required. I had a little reference book that wasn't that much help, but I tried to keep things in order based on that convention. |
|||
![]() |
|||
![]() |
|||
![]() |
|||
TUESDAY, AUGUST 22, 2006 |
|||
![]() As it turned out, I pretty much stood around and watched, and advised as needed on the locations of the various fixtures, what could be cut, etc. I was very glad I hired someone who knew what they were doing, because I really hadn't know where to start. |
|||
![]() |
|||
![]() |
|||
![]() Because it was impossible to run the piping for the second floor without being exposed, we had always planned to install closed ceilings in the pantry and downstairs bath. To hide the piping you see here, and the remainder of the drain pipes coming tomorrow and beyond, I'll strap the ceiling with 2x6 on edge, which will hide all the pipe once drywall is installed. This is deeper than I had anticipated, but it will work nonetheless. You'll see this step fairly soon. I also managed to get a little more wiring done, before and after Bunny's time on site, but it hardly bears mentioning. |
|||
MONDAY, AUGUST 21, 2006 |
|||
I got a call from Bunny at 6:15 saying
that he'd have to come tomorrow rather than today because of some
other business. Sigh. Oh well. I decided to just
press on with the wiring today and make some good progress. I worked all day on the electrical, and made good progress on the first floor, including running all of the longest circuits (to the southern end of the house, the opposite end from the electrical service panel) and most of the circuits in the log walls--the most difficult part. |
|||
![]() |
|||
![]() I was just glad that I didn't have to pay an electrician to do this work. It would be an expensive wiring job, just for the time involved and some of the other considerations specific to the log construction. |
|||
![]() (The outlet boxes themselves are just out of frame in the picture above. Sorry for the bad composition and lack of context.) |
|||
I ran some of the wiring into the stud walls on the first floor as well, though I avoided walls where plumbing would be installed so that I could later run the wires around the plumbing, rather than the other way around. Similarly, I did not run any wires to the second floor, choosing to wait until the plumbing was installed so that I could decide on the best wiring route. This should all be clear after tomorrow. I chose some convoluted paths for my wires for some of these interior walls, as I wanted logical outlets to be attached together, rather than just the closest ones. For example, I wanted all three boxes in the hallway to be on one circuit--but they were on opposite sides of the hall, with an exposed pine ceiling and beams above, so connecting these boxes required running the wire back through the floor and then over to the other side as required. I've always hated wiring in some of the houses I've experienced, where the most random things are connected on the same circuit. My old house in North Yarmouth was the poster child for this--absolutely terrible. It would take me 20 minutes to just find the right circuit to shut off to change out a light fixture or something, as one light in the kitchen might be on the same circuit with the upstairs bath, while the other was on the living room. Plus the box was marked poorly and inaccurately. Therefore, despite the extra time and extra wire required, I had the opportunity to build an electrical system that I liked, so I planned my routes carefully, and kept the wiring neat and securely fastened to the framing as needed. At the same time, I didn't want to end up with a ridiculous number of circuits, so I banded together things like the hallway and pantry outlets, most of which will never see use and certainly not at the same time. Again, this made for a more complicated installation, but better in the long run. |
|||
![]() By the end of the day, all the wiring was run in the log walls, except for three outlets in Heidi's office. It was nice to have that done. The rest of the wiring should be easy by comparison. |
|||
SUNDAY, AUGUST 20, 2006 |
|||
![]() I reversed the lower cross braces on the second sawhorse so that the two would stack neatly. While I was at it, I built a simple X-brace support that I'd use to hold my 1000' reels of wire during installation, allowing for easy dispensing. |
|||
![]() I also began drilling some holes through the floor joists in the basement. I began with some 2" holes (since I had the bit chucked into the drill) nearest the panel and through all the joists to the stairwell, where I thought I would end up running many wires. I also drilled the 2" holes on the other side of the house, through several joists leading to the first interior wall leading upstairs, where I'd run many of the second floor wires.
|
|||
Then, I changed to my 1" auger bit and drilled pairs of holes through the remaining joists on the front of the house, and also several holes through the carrying beam in the center of the house to the other side. I got tired of drilling holes at this point, and moved on to other things.
|
|||
I spent some time marking a level line and then installing most of the outlet boxes on the stud walls on both floors. I didn't install switch boxes at this point since I still had to figure out what lights were needed and where the switches might go. Plus, a box I thought was full of double-gang boxes turned out to contain only one or two, the rest being triples. In any event, I planned to run all the outlet wiring first, and then the lighting and switch wires, since I didn't intend to share circuits between the two (this always ends up being overly complicated, in my experience, and I'd rather run the extra wire). I installed lots of outlet boxes, including additional boxes for Internet, phone, and TV.
|
|||
![]() Each box took a minute or two to modify and install; once modified, the boxes fit easily into the openings in the walls, and I secured them with a drywall screw. At this time, I knocked off for the day. My phone had died, so I had no way of telling the time, but as I had worked straight through lunch, I figured it was about 3:00--a good enough day for a Sunday. When I got back down to the shop, though, I discovered it was 4:30. |
|||
SATURDAY, AUGUST 19, 2006 |
|||
Now that I had the Dutch door all painted and sealed, I decided it was time to install it, and to seal up both door openings. Since the two doors required the exterior trim in order to fully install them, I had postponed this work for several weeks, deeming it less important than other tasks. During rain showers since that time, water had still come in the Dutch door entrance, which didn't harm anything, but it was time to seal the opening off properly. The fact that Sunday was predicted to be a rainy day was also a factor in my decision. | |||
The first order of business was to notch out the exterior logs for the trim. During the installation of the window and door bucks, I had chosen to ignore the recommendation to make a saw cut into the ends of the logs at the outer edge of the bucks; if I had done this, then theoretically I was supposed to use a skilsaw to make a second cut on the outside of the logs, which would intersect perpendicular with the first cut. The waste material could then be chiseled out. I thought it would be better to use a router to notch the logs, however, and would provide a cleaner cut. So I didn't make the saw cuts, and now I had to figure out some sort of a router jig to use to make the cuts. After setting up some staging outside the Dutch door, I puzzled over the jig. I wanted to build a jig that didn't require any sort of fasteners to be driven into exposed areas of the logs, and eventually came up with a plan that I thought would work. I had to make a couple trips down to my shop to rip some wood on the table saw, so between this and the thought process, it took quite some time to build the jig. My jig included narrow strips of pine that I screwed into the window bucks right next to the door opening, and then cross braces to hold a straightedge out on the log surface. This eliminated the need to nail or screw into the logs where it might be visible. Unfortunately, once the jig was built, I realized that it just wasn't going to work very well, partly because each window and door opening was a little different and the jig probably wouldn't work as a universal thing. So despite the time invested, I trashed it, and went in a different direction. |
|||
![]() |
|||
![]() |
|||
![]() |
|||
With the cuts made on all sides (I didn't have to rout the top, since the large gap above the door was, thankfully, just the right height for the 3-1/2" trim), I applied a bead of Sikaflex to the exterior seam of the door buck, and then installed rubberized flashing tape over the opening, keeping the edge inside of area that the trim would cover. This required cutting about an inch off the material. Then, I measured, cut, and installed the 5/4 x 3-1/2" flat pine trim, using more Sikaflex behind and securing it with 2-1/2" galvanized finish nails into the door casing and bucks. |
|||
It had taken all morning to complete the first door. But now I had a system that worked, and I knew that the front door would go much more quickly, and that the windows, when I got to them, would also go quickly. I spent more time fine tuning the door fit from inside and getting it operating properly. |
|||
![]() |
|||
During the remainder of the afternoon, I finished securing the front door from the inside, allowing me to finally operate it normally, and then installed the door hardware and locksets on both doors to allow for convenient operation and securing against wind. I couldn't believe this process had taken all day, but sometimes that's just how it is. Note that the 2x4 at the bottom of the Dutch door is not part of the trim, and is only temporary to support the overhanging edge of the door threshold. I don't want you to think that somehow I wasn't aware of the horrible gaps on the ends. |
|||
|
|||
FRIDAY, AUGUST 18, 2006 |
|||
The morning began on an auspicious
note when I successfully reached Bunny at 7:00, and set up the work
to begin on Monday. Phew. Heidi and I spent the morning on house-related errands, beginning with a trip out to Moose Creek to meet with Wendy, the kitchen designer, etc. It was time to nail down our kitchen and bath cabinet choices and designs. The meeting was surprisingly short, at an hour or so, and she promised us an initial design later in the day. On the way home, we stopped in to Home Despot in Augusta for some pipe fittings that I had somehow forgotten yesterday, leaving me short on a few items. This was partly thanks to the fact that some of the items in the bins yesterday had been in the wrong spot, and I hadn't noticed until I got home. I also picked up some electrical supplies that I might need over the weekend. Next, it was on to Sherwin Williams, where I had them color match the Andersen forest green paint that covers our windows and doors, so that I could paint the Dutch door and the front door. The color match seemed to come out very nicely. We arrived home after lunch, and after I reviewed and commented on our initial kitchen design--which was waiting in my email--I went up to do some simple projects. I applied the two coats of poly to the final side of the truss beams, and two coats of the new green paint to the Dutch door. This was pretty much it for the afternoon. No pictures...sorry! I do have this to say: true divided light windows (with the individual panes) are great--attractive and classy--but I sure am glad I only have the one door to paint that contains these! The add-on grills on the remaining doors and windows may not look quite as nice, but they sure are easier! |
|||
THURSDAY, AUGUST 17, 2006 |
|||
![]() Despite my early start, it was 9:30 before I got back to the house. Then, I spent an hour unloading and organizing the plumbing parts. This seemed overwhelming. I was very much looking forward to getting this portion of the job over with! |
|||
![]() |
|||
![]() |
|||
![]() |
|||
![]() I tried to reach Bunny several more times during the day and into the evening, but to no avail. |
|||
WEDNESDAY, AUGUST 16, 2006 |
|||
![]() I began in the downstairs bathroom where I left off last night, completing the last wall down to floor level. Then, I sanded two very small sections of exposed log next to the Dutch door in the hallway before moving on to Heidi's office and craft room. |
|||
![]() |
|||
![]() |
|||
![]() |
|||
After lunch, I applied two coats of poly to the office, bathroom, and pantry, which went smoothly without issue. It felt great to be covering the final section with poly. I received a plumbing materials list from Bunny Brann, and spent some time late in the day going through the pieces I had purchased earlier in the week and checking them off against the list. There were a lot of pieces that I didn't need, and many more pieces that I would need, so I planned another pre-dawn trip in the morning to pick up the remainder. I had hoped to get the tub lifted into the house today, but the 4x8 truss beams I had been waiting for arrived on a small truck with no boom and a different driver--rats! That will have to wait for another day. I immediately put the fresh, white, clean beams inside the house for safekeeping; I planned to lightly sand them and apply the poly tomorrow, before their installation. Not only would this mean that once installed the truss would be complete, without a need to climb to the ridge to finish it, but pre-finishing would also protect the wood during whatever time period should elapse before I can get them installed. I'll have to see what Bob's schedule will allow, as I'll need his assistance. |
|||
![]() |
|||
The heat guys finally finished up today, after another full (for them) day onsite. The end result looked excellent, though, and it was nice knowing that the heating system was ready to go as soon as necessary. |
|||
Click here to go to the logs from August 1 to August 15. |
|||
|