Hattie Mae | Monday, June 1, 2009

I got started by sanding the Alexseal filler that I applied on Friday afternoon.  Afterwards, I vacuumed up the dust, and then preliminarily solvent-washed the deck, hull, and hatches before retaping several areas that required it.

Next, I vacuumed and washed down the staging and shop floor as necessary to remove the fine sanding dust from last week's sanding.  Then, later I re-cleaned the deck and hull using the Alexseal wipe-down solvent as a final cleaning measure, and prepared the finish primers for tomorrow's spraying session, along with other preparations for the day's work, including preparing the spray equipment and laying some paper on the deck in areas where I'd have to walk or kneel  during the first steps of the primer application.


         

         

 


Total Time Billed on This Job Today:  5.25  hours