Skeedeen Phase 7-10

Boat:

Skeedeen, a 1987 24' Crosby Striper

Schedule:

Project Schedule: October 2021 – November 2021, plus March/April 2022

Project Scope:  Brightwork maintenance; Miscellaneous Seasonal Maintenance, new canvas

Project Complete:  32.5 Total Hours

 

Begin Daily Project Logs

March 30, 2022

Skeedeen Phase 7-10

Wednesday

With better weather hopefully on the horizon and a need to finish up the new canvas work, the owner asked that I uncover the boat and remove the frame, after which I set up the bimini bows to be ready for Jason to fit the top (which was complete) and pattern the side curtains.

A day or two later, with decent weather, Jason arrived to fit the top and make some final sewing alterations to complete the support pockets, the center one of which he’d left unsewn to ensure the fit was correct.  Then, later that day and with the top fully sewn, he returned to pattern the two side curtains, which he’d build during the rest of the week.

Total time billed on this job today: .75 hours

0600 Weather Observation: 26°, clear. Forecast for the day: Sunny, 47°.