Matthilda 2

Boat:

Matthilda, a 1962 Pearson Electra 22' Sloop

Schedule:

Project Schedule:  Winter 2026-2027

Project Scope:  Deck recore and refinishing; Rebed hardware; (Hopefully) Hull refinishing; Interior work; minor rigging and electrical work; More or Less TBD

Begin Daily Project Logs

November 3, 2026

Matthilda 2

Tuesday

Ready to start the project in earnest, I began by documenting the boat inside and out, starting with the hull.  While deck core repairs were top of the priority list for this project and the owner’s budget, we hoped to be able to restore the hull as well, though not till the deck work was well underway and I had a better idea of the time involved.

The decks were soft in most areas–sidedecks, foredeck, and coachroof, although I hadn’t done a thorough examination yet.  So repairs would likely involve all deck areas, with required cosmetic restoration to follow.  For now, I documented the existing condition and hardware locations for future reference.

Before beginning the hardware removal, I took a few moments to measure and document the existing heights of the boottop and bottom paint stem and stern, which I’d use sometime later in the project assuming that we proceeded with hull work.  I made some simple reference measurements from the transom and top of the stem as needed to give me the points I needed.  At the bow, I removed the tall bow stop on the trailer to give me access for this measurement, and added a V-stand beneath the bow for additional support since I wasn’t sure how crucial the bow stop was in stabilizing the boat.  I didn’t need to do this little job now, but it’s one I like to do early in the project so I don’t forget.

After collecting tools and such, I spent the remainder of the day removing deck hardware, starting at the stem and eventually working my way aft to the forward end of the cockpit.  I removed the bow pulpit, cleat and chock, and the cowl vent from the foredeck.  Then, I removed the chainplates–three per side–which was a time-consuming job since access was difficult because of the shape of the chainplate knees (forward lowers in particular), and it turned out all the bolts were corroded and broke during removal.  Eventually I removed all the bolts (3 in each chainplate, or 18 total) and removed the chainplates.  I’d have to clean up and inspect the bronze chainplates later to determine whether or not they needed replacement.

The four deadlights featured bronze frames inside and out, with bronze screws through the outside frame and into threaded holes in the interior frames.  Fortunately, these screws came out easily, and I determined that all the lenses were actually plastic, not glass (the owner and I had discussed this when he dropped off the boat), which would make for easy replacement.  The bronze frames were in good condition.

By the end of the day, I’d made it as far as the cockpit, including removing two small jib tracks (which were corroded at the screw locations to the extent that the tracks broke during removal), along with the handrails and various coachroof hardware.  Next time, I’d continue aft and see if I could make it all the way to the transom.

 

Total time billed on this job today: 6.75 hours