August West Phase 2-6

Boat:

August West, a 1986 22' Cape Dory Typhoon Sr.

Schedule:

Project Schedule: September 2026

Project Scope: Repaint nonskid, misc.

Project Complete:  26 Total Hours

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

September 25, 2026

August West Phase 2-6

Friday

The fresh nonskid paint had had over 24 hours’ cure time, so now I removed all the masking tape to reveal the finished product.

Work remaining:  a few bits of hardware to reinstall; secure the mast back on deck; check a couple things for the owner and remove the battery; and cover and store the boat outdoors.

Total time billed on this job today: 1.5 hours