During the morning hours, I made the final preparations required for hull primer.  I masked off the deck and covered it with plastic sheeting, then masked the waterline and installed masking paper beneath to avoid undue overspray on the bottom.  As usual, I solvent-washed and tacked off the hull, and washed down the shop, which fortunately had remained quite clean during the past week's work.

    
    


With preparations complete, I applied three coats of Alexseal finish primer over the period of a couple hours, and left it to cure overnight.

         



In other news, the template work for the dodger and interior cushions that had been planned last Friday was firmly rescheduled for one week from today, Monday the 25th.


Total Time Billed on This Job Today:  5.25 hours