Project Schedule:  January 2025 – March 2025

Project Scope:  Refinish brightwork, hull paint, sundry small tasks

Project Complete:  216.5 Total Hours

Begin Daily Project Logs

March 13, 2025

Danusia Phase 2-48

Thursday

With the pedestal recoating complete, I removed all the masking, then reassembled the pedestal with the steering wheel and cockpit table to complete the related work.