Danusia Phase 2-12

Boat:

Danusia, Cape Dory 31

Schedule:

Project Schedule:  October 2024 – (Ongoing)

Project Scope:  Refinish brightwork, hull paint, other work TBD

Begin Daily Project Logs

January 17, 2025

Danusia Phase 2-12

Friday

After lightly sanding the brightwork with 320 grit, I applied the third coat of varnish to all areas.

Total time billed on this job today: 4.5 hours