Aquasport 5

Boat:

2000 Aquasport 175 Center Console

Schedule:

Project Complete:  11.5 total Hours

Scope of Project:   Determine waterline; prep and paint bottom; remove old striping and create new boottop; install kicker bracket

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

April 21, 2016

Aquasport 5

< Back to Aquasport

Thursday

Earlier, I’d finished up the fiberglass backing plate for the outboard bracket–sanding, primer, topcoat (the same gray I used on the boottop).  Now, with the transom prepared and the backing block ready, I completed the bracket installation, securing it with four bolts, backing plates, and large washers.

< Back to Aquasport

Total time billed on this job today:  1 hour

0600 Weather Observation:
25°, clear.  Forecast for the day:  sunny, 70s