Boat:

2000 Aquasport 175 Center Console

Schedule:

Project Complete:  11.5 total Hours

Scope of Project:   Determine waterline; prep and paint bottom; remove old striping and create new boottop; install kicker bracket

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

April 11, 2016

Aquasport 3

< Back to Aquasport

Monday

Now that the boottop primer was dry, I lightly sanded it, then solvent-washed to prepare for the topcoat.  For this, I chose a platinum gray paint that I had on hand from who knows what project, but I thought it would be a nice subtle color for this application.  Actually, the choices in this project were as much about what I had on hand and could use up as they were about final appearance.  The paint covered well, and later in the day I decided that the one coat was ample, so I removed the masking tape, completing the paint work on this boat.

Total time billed on this job today:  .5 hours

0600 Weather Observation:
32°, cloudy.  Forecast for the day:  occasional showers, clouds, high in the 40s