Scupper 7

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

Early phase in September 2017 Hardware removal and early assessment

Phase 1 March 2018 – October 2018:  Dismantling, surface prep, systems removal, repairs, structural work

Phase 2 Coming in Winter 2018-2019:  Interior and more

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

October 3, 2017

Scupper 7

< Back to Scupper

Tuesday

After some final cleanup, I took the short step of filling all the raw fastener holes in the deck with some inexpensive latex household caulking compound, just to minimize (and hopefully prevent entirely) any leakage through the holes that could occur beneath the boat’s cover once I moved her out for storage.  The temporary sealant would be easy to remove during surface preparations at a later stage of the project.

Afterwards, to make room for another boat arriving soon I moved Scupper outdoors for storage till her real project time, and covered her simply with a tarp to keep out the weather.

Total time billed on this job today:  1.75 hours

0600 Weather Observation:  30°, clear.  Forecast for the day:  sunny, 60s