Scupper 58

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

Early phase in September 2017 Hardware removal and early assessment

Phase 1 March 2018 – October 2018:  Dismantling, surface prep, systems removal, repairs, structural work

Phase 2 Coming in Winter 2018-2019:  Interior and more

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

August 20, 2018

Scupper 58

< Back to Scupper

Monday

Continuing on the hull, I worked during the morning to sand the starboard side with 220 grit, smoothing the fresh primer.

After resetting the staging so I could reach the decks again, I finished up the work on deck, sanding the foredeck, sidedecks, poop deck, and cabin trunk/outer coamings as needed to smooth the primer.

Total time billed on this job today:  7 hours

0600 Weather Observation:  50°, clear.  Forecast for the day:  Sunny, 75°